EAST ORANGE - DISTRICT WIDE SCHOOL EXPANSION PROGRAM

Project Name: EAST ORANGE - DISTRICT WIDE SCHOOL EXPANSION PROGRAM
Project Address: East Orange, NJ

Program Contract Amount:

$47,407,867
Project Executive: Mark D. Hall
Project Manager: Scott V. Hall/Joseph Isdanavage
Executive Supervisors: Roy Ralph / Richard Lefebvre
Owner's Name/Contact Person: East Orange Board of Education - Everett Jennings, CCE
Owner's Address: 715 Park Avenue, East Orange, NJ 07017
Owner's Phone/Fax Numbers:

Phone: 973-266-5761 / Fax: 973-266-5854

Architect's Name/Contact Person: .Mr. David Chase
Architect's Phone/Fax Numbers: Phone: 609-577-0304
Description of Project:















HART MIDDLE SCHOOL
  • Design/Build emergency stabilization of exterior walls/foundations and underpinning
  • Phased while occupied
  • Double crews during summer months
  • Complete renovation and addition to this 170,000 sq.ft., 3 school complex
  • New reception lobby and theatre/stage/control room
  • New gymnasium and athletic equipment
  • New kitchens and cafeterias (2)
  • New classrooms and administrative offices (26)
  • Existing classrooms renovated (40)
  • Restored exterior brick masonry, brick replacement/repointing
  • Extensive site utilities and landscaping
  • ADA upgrades
  • Project completed five months ahead of schedule

RECONSTRUCTION OF MARTEN'S STADIUM/PAUL B. ROBESON STADIUM
  • Selective Removal of Trees
  • Demolition of existing structures
  • Regraded site contours
  • Extensive underground utilities and track/field drainage systems
  • 10,000 seat Grandstand facilities
  • Locker rooms, restrooms, food service, mechanical rooms
  • New press box and elevator
  • All handicap accessible
  • Regulation size football field; astroturf surface
  • Rubberized perimeter running track and field events area
  • Extensive landscaping and parking facilities
  • Project completed one month ahead of Schedule
ASHLAND ELEMENTARY SCHOOL
  • Overall new site construction and building construction
  • New 100,000 sq. ft. elementary school
  • Steel frame with concrete decks, three stories
  • All masonry exterior and interior
  • New gymnasium
  • New Cafeteria and full service kitchen
  • Reception/lobby area
  • Thirty (30) new classrooms
  • New baseball field and activities areas
  • Paved sports/play yard
  • Substantial landscaping
  • Rehabilitation of existing roadways adjacent to school
  • Project completed one month ahead of schedule
ALTHEA GIBSON EARLY CHILDHOOD EDUCATION ACADEMY
  • 22,000 sq. ft. state of the art steel and masonry facility
  • Accented by large glazed curtain walls and clearstory windows
  • An award winning facility featuring a plethora of building materials and textures in bold and primary colors to peak a child's interest and senses
  • 10 large multi-functional activity/classrooms with toilet rooms
  • Each classroom pair interconnected by a carpeted, light-filled, stepped story-telling area
  • Fully equipped nurse's station
  • Separate Guidance Counseling and Testing wing
  • Glazed curtain wall multi-purpose room
  • Multi-purpose room has all-purpose flooring for athletic play or cafeteria use
  • Kitchen and an equipped stage area is connected to the multi-purpose room
  • Project completed within 5 months on a super-accelerated schedule